E-mail: výsledky kaizen projektu
Majster Marek posiela vedeniu závodu zhrnutie zlepšovacieho projektu na lise. Všimni si čísla, kauzatív a pripísanie zásluh tímu.
To: Plant management
Subject: Kaizen results – press 4 changeover
Dear all,
I'm pleased to share the results of the six-week kaizen project on press 4.
Starting point: An average changeover took 47 minutes, and press 4 had become the main bottleneck in the body shop. Availability was only 68%.
What we did: We filmed six changeovers and broke them down into 38 steps. The operators found that 21 of these could be done while the press was still running. We had a second tool trolley built so that the next die can be prepared in advance, and we got the supplier to modify the clamps so they can be changed without special tools. We also had the floor markings repainted to shorten walking distances.
Results: Average changeover time has fallen to 14 minutes. Availability has risen to 81%, and OEE on press 4 has improved by nine percentage points. The total cost was under €4,000.
Next steps: We will standardise the new procedure and train the night shift by the end of the month, then apply the same approach to press 2.
Most of the ideas came from the operators themselves – a big thank you to the whole team on line 3.
Best regards,
Marek